Oyu Tolgoi announces Q3 2020 performance results

  • Globally competitive safety performance continues
  • Awarded the Copper Mark for responsible production
  • On track to achieve 2020 copper and gold production guidance
  • Paid US$201 million in taxes, fees and other payments to the Government of Mongolia
  • Spent US$273 million on national procurement

Oyu
Tolgoi released the latest edition of its performance scorecard,
highlighting key performance metrics for the third quarter of 2020, and
provided an update on underground development, and its continued
prevention measures on COVID-19.

Oyu Tolgoi is proud to be
awarded the Copper Mark, the copper industry’s new responsible
production recognition programme. The Copper Mark requires the company
to demonstrate that it meets over 30 criteria for responsible
environmental, social and governance operating practices. Oyu Tolgoi
chief executive officer, Armando Torres, said, “We are pleased to be
among the first in the copper industry to be awarded the Copper Mark,
demonstrating our commitment to responsible mining and transparency. We
achieved this together with all our stakeholders and communities in
Mongolia. We will continue upholding the highest social and
environmental standards and draw on the advice of environmental experts
and the communities in which we operate.”

The company is
continuing its close monitoring of the COVID-19 situation with its
Business Resilience Team and is taking preventive measures throughout
the operations. Our preventive protocols are in full compliance with the
guidance and decrees issued by the Government of Mongolia, State
Emergency Committee, and the local authorities in Umnugovi province and
Khanbogd soum.

Q3 2020 Operational Update

  • Open pit operations continued uninterrupted.
  • Achieved an All Injury Frequency Rate (AIFR) of 0.17 per 200,000 people/hours worked.
  • Maintained
    excellence in water saving, using 0.35 cubic metres of raw water per
    tonne of ore processed compared to our target of 0.55, and achieving an
    average water-recycling rate of 87.5 per cent, compared to our target of
    80 per cent, at the end of the third quarter.
  • Ninety-four per cent of Oyu Tolgoi’s workforce were Mongolian citizens.
  • Paid
    US$201 million in the form of taxes, fees and other payments to the
    Government of Mongolia as of the end of the third quarter of 2020. Since
    2010, Oyu Tolgoi has paid US$2.8 billion in taxes, fees and other
    payments including VAT to Mongolian suppliers.
  • Collaborated with
    703 suppliers by the end of the third quarter of 2020, of which 468 are
    national businesses, which accounts for 73 per cent of the total
    operations procurement spend.
  • The updated 2020 Performance Scorecard can be viewed here .

Q3 2020 Production Update

  • Mined
    copper production from the open pit was 28 per cent higher than the
    same quarter of 2019 and steady quarter-on-quarter reflective of the
    move to higher grade areas of the open pit in 2020, primarily due to
    accelerated mine development and production phasing. Access to higher
    copper and gold grades is expected to continue for the remainder of
    2020, which was originally planned for the first half of 2021.
  • Q3
    2020 mill throughput was slightly higher than Q3 2019 due to slightly
    higher mill availability and an increased milling rate associated with
    softer ore.
  • Copper and gold production guidance for 2020 remains
    within the ranges of 140,000 to 170,000 tonnes and 155,000 to 180,000
    ounces respectively, with gold production trending towards the higher
    end of the range.

Oyu Tolgoi Production Data

All data represents full production and sales on a 100% basis

3Q

2019

4Q

2019

1Q

2020

2Q

2020

3Q

2020

9 months

2020

9 months

2019

Full year

2019

Open pit material mined (‘000 tonnes)

24,844

28,122

26,834

23,218

23,979

74,032

73,195

101,316

Ore treated (‘000 tonnes)

10,040

11,088

10,889

9,645

10,072

30,606

29,689

40,777

Average mill head grades:

Copper (%)

0.37

0.42

0.42

0.47

0.45

0.45

0.46

0.45

Gold (g/t)

0.14

0.15

0.15

0.19

0.21

0.18

0.44

0.29

Silver (g/t)

1.03

1.06

1.14

1.22

1.22

1.19

1.16

1.13

Concentrates produced (‘000 tonnes)

131.3

152.6

164.5

169.9

168.5

502.9

552.1

674.6

Average concentrate grade (% Cu)

21.7

21.6

21.4

21.5

21.5

21.5

21.7

21.7

Production of metals in concentrates:

Copper (‘000 tonnes)

28.4

32.9

35.2

36.5

36.3

108.0

113.4

146.3

Gold (‘000 ounces)

26

24

26

31

37

94

218

242

Silver (‘000 ounces)

191

190

214

212

219

645

677

867

Concentrate sold (‘000 tonnes)

157.0

157.5

125.9

194.3

167.9

488.1

567.2

724.7

Sales of metals in concentrates:

Copper (‘000 tonnes)

32.4

32.3

25.8

39.7

34.4

99.9

117.6

149.9

Gold (‘000 ounces)

35

25

20

31

34

84

249

274

Silver (‘000 ounces)

207

244

146

220

201

566

652

896

Metal recovery (%)

Copper

75.1

74.2

74.3

79.1

78.9

77.4

80.3

78.7

Gold

54.7

48.2

46.0

52.0

53.7

51.0

66.2

63.6

Silver

56.0

53.5

51.5

55.8

54.6

54.0

59.6

58.1

Underground Development Update

  • Work
    on the project has continued to progress despite COVID-19 controls and
    ongoing international travel restrictions issued by the Government of
    Mongolia.
  • Care and maintenance activities continue at Shafts 3
    and 4; some commissioning activities have advanced in preparation for
    shaft sinking, including rope installation on Shaft 4. Further progress
    will require the remobilisation of international shaft sinking
    specialists and preparation is underway to mobilise some of these
    contractors before the end of 2020 (subject to change due to the current
    COVID-19 restrictions in the country).
  • Overall, underground
    lateral development has now reached 45,858 equivalent metres, or around
    90 per cent of the required development to support firing of the first
    drawbell.
  • All surface infrastructure required for sustainable
    production is complete and the team is focused on progressing the
    critical underground Material Handling System 1 (MHS1) to the stage
    needed ahead of the first drawbell firing. The balance of project
    infrastructure to be delivered post completion of MHS1 is not needed for
    sustainable production, however, it is needed to support the production
    ramp-up profile.
  • Preliminary indications from the definitive
    estimate process are that first sustainable production is trending
    towards the earlier months of the October 2022 to June 2023 range. The
    estimated development capital cost remains within the range of US$6.6 to
    US$7.1 billion. This assessment has now been updated to include known
    cost and schedule impacts from COVID-19 and assumes an easing of travel
    restrictions and COVID-19 related controls from the time of reporting.
    This remains subject to ongoing review as part of finalising the
    definitive estimate of cost and schedule for Panel 0, expected in the
    fourth quarter of 2020.
  • On 3 July, we announced the completion
    of an updated feasibility study (OTFS20) prepared in accordance with
    Mongolian regulations and standards. Registration of the Updated Reserve
    and Resource Report (RR19) has been delayed beyond the 150 day period
    of review since its submission in February 2020. Registration of RR19
    is required before formal consideration and acceptance of the OTFS20. In
    accordance with the 2009 Investment Agreement and Mongolian regulation,
    the Government of Mongolia is required to consider each of the RR19 and
    OTFS20 within 150 days from submission. The OTFS20 also forms the
    basis for the uplift in the overall underground project cost that is
    required to be approved prior to the under-cut decision (decision to
    initiate caving) in 2021.

Other Updates

  • Oyu
    Tolgoi has been working to progress power negotiations with the
    Government of Mongolia as required under the terms of the Power Source
    Framework Agreement Amendment signed in June 2020:

    • An extension
      of power import arrangements with China’s Inner Mongolian Power Company
      is required by 1 March 2021 in order to ensure sufficient certainty on
      future supply of power before the under-cut decision is taken.
    • A
      Power Purchase Agreement (PPA) for power supply to Oyu Tolgoi from a
      State Owned Power Plant at Tavan Tolgoi that will be funded by the
      Government of Mongolia is required to be executed by 31 March 2021.
    • Following
      the agreement to purchase some power from the Mongolian national grid,
      on 3 September 2020, Oyu Tolgoi LLC and the Southern Region Electricity
      Distribution Network executed a PPA to supply power to the Oyu Tolgoi
      camps.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *