Oyu Tolgoi announces Q1 2021 performance results

  • Continued its globally competitive safety performance
  • Strengthened our COVID-19 response and mitigation measures
  • Maintained its highest water use efficiency per tonne of ore production
  • In-country spend reaches US$12.3 billion
  • Spent US$98 million on national procurement

Oyu
Tolgoi released its latest performance scorecard, highlighting key
performance metrics for the first quarter of 2021, providing an update
on the underground development, and its ongoing COVID-19 mitigation
measures.

The first quarter of 2021 has been challenging due to
the COVID-19 global pandemic and increase of community cases in
Mongolia. We are constantly adapting to the changing circumstances to
prioritize the health and safety of our workforce, suppliers and
communities.

A site-wide lockdown was implemented in March for
two weeks to mitigate the potential COVID-19 transmission risks on site.
Self-isolation controls were quickly mobilized at camp. Currently,
site-wide COVID-19 testing is in place and preparations to rollout a
vaccination programme are progressing.

Oyu Tolgoi chief executive
officer, Armando Torres, said, “We would like to express our gratitude
to the Government of Mongolia, all levels of the State Emergency
Commission, the Ministry of Health, the Ministry of Mining and Heavy
Industry, and all other relevant agencies and frontline personnel
working hard to keep us safe during this unprecedented time. I would
especially like to thank our employees, communities, contractors, and
suppliers for their hard work, perseverance, unwavering commitment and
ability to quickly adapt to rapidly evolving situations.”

Despite
the challenges, Oyu Tolgoi has maintained its business continuity while
protecting its people and communities. COVID-19-related limitations
around the movement of goods and people, border crossing restrictions,
and enhancing our on-site controls, however, have impacted operations
including the underground development, and copper concentrate shipments.
First-quarter shipments have been affected by Chinese border
restrictions due to increased cases of COVID-19. We declared force
majeure on shipments from 30 March and continue to work closely with
authorities and our customers to manage the risk of supply chain
disruptions. Oyu Tolgoi vaccinated all its copper concentrate shipment
drivers and logistics support teams on site, and has a number of
controls in place related to disinfecting vehicles and testing to
mitigate transmission risk. We partially resumed cross-border
concentrate shipments into China on 15 April, however, the situation
continues to be fluid with the COVID-19 resurgence in Mongolia.

Operational Update

  • Prioritised
    the safety and achieved an All Injury Frequency Rate (AIFR) of 0.20 per
    200,000 people/hours worked. This still indicates Oyu Tolgoi’s strong
    safety performance among other operations of Rio Tinto where the average
    AIFR stood at 0.35 for the same quarter.
  • Maintained
    excellent water-conservation practices, achieving the highest water use
    efficiency rates per tonne of ore production, using 0.37 cubic meters of
    raw water per tonne of ore processed – three times less than similar
    operations worldwide. Achieved an average water-recycling rate of 88.7
    per cent, compared to a target of 80 per cent.
  • 96 per cent of Oyu Tolgoi’s workforce are Mongolian citizens.
  • Paid
    US$417 million in the form of taxes, fees and other payments to the
    Government of Mongolia in the first quarter of 2021. Since 2010, Oyu
    Tolgoi has paid US$3.3 billion in taxes, fees and other payments,
    including VAT to Mongolian suppliers.
  • Partnered with 494
    suppliers in the first quarter of 2021, including 431 national
    businesses, accounting for 77 per cent of the total operations
    procurement spend.
  • Q1 2021 Performance Scorecard can be viewed here.

Production Update

  • Mined
    copper production from the open pit was 29 per cent higher than the
    same quarter of 2020 with the anticipated move to higher grade from the
    open pit, leading to higher head grade and copper recovery. In the first
    quarter, pit phasing delivered higher gold production (+457%) compared
    to the same period in 2020. Access to higher copper and gold grades is
    expected to continue throughout 2021. However, the open pit wall failure
    experienced in the fourth quarter of 2020, combined with the cumulative
    effects of COVID-19 mitigation measures, have resulted in a downward
    revision in gold production guidance for 2021, from 500,000 – 550,000
    ounces to 400,000 to 480,000 ounces, while the copper guidance range has
    expanded from 160,000 – 180,000 tonnes to 150,000 – 180,000 tonnes.

Oyu Tolgoi Production Data

All data represents full production and sales on a 100% basis

1Q

2020

2Q

2020

3Q

2020

4Q

2020

1Q

2021

Full-year

2020

Open pit material mined (‘000 tonnes)

26,834

23,218

23,979

23,663

22,588

97,694

Ore treated (‘000 tonnes)

10,889

9,645

10,072

9,594

9813

40,200

Average mill head grades:

Copper (%)

0.42

0.47

0.45

0.50

0.56

0.46

Gold (g/t)

0.15

0.19

0.21

0.41

0.68

0.24

Silver (g/t)

1.14

1.22

1.22

1.16

1.29

1.18

Concentrates produced (‘000 tonnes)

164.5

169.9

168.5

190.2

201.9

693.1

Average concentrate grade (% Cu)

21.4

21.5

21.5

21.9

22.5

21.6

Production of metals in concentrates:

Copper in concentrates (‘000 tonnes)

35.2

36.5

36.3

41.6

45.4

149.6

Gold in concentrates (‘000 ounces)

26

31

37

88

146

182

Silver in concentrates (‘000 ounces)

214

212

219

231

255

876

Concentrate sold (‘000 tonnes)

125.9

194.3

167.9

181.5

186.3

669.6

Sales of metals in concentrates:

Copper (‘000 tonnes)

25.8

39.7

34.4

37.9

39.0

137.8

Gold (‘000 ounces)

20

31

34

66

111

150

Silver (‘000 ounces)

146

220

201

194

207

760

Metal recovery (%)

Copper

74.3

79.1

78.9

85.9

86.3

79.6

Gold

46.0

52.0

53.7

68.8

72.2

58.6

Silver

51.5

55.8

54.6

64.3

65.3

56.4

Underground Development Update

  • Work on the underground Material Handling System 1 advanced in line with the definitive estimate[1]
    outlined in December, with sustainable production expected in October
    2022 and development capital of $6.75 billion. Progress on shafts 3 and
    4, and other planned works, have been significantly affected by COVID-19
    restrictions around people movements. We are currently reviewing the
    implications on panels 1 and 2 ramp-up, which shafts 3 and 4 support,
    and will provide an update in due course.
  • In addition to ongoing
    flight restrictions and government-imposed lockdowns – including an
    “all-out readiness state” declared by the Mongolian State Emergency
    Commission in November 2020 and again in April 2021 – Oyu Tolgoi imposed
    a site-wide quarantine period and all underground construction was
    temporarily halted for two weeks in March to mitigate potential
    transmission risk onsite. The impact of these additional restrictions is
    ongoing and still being assessed.

Other Updates

  • On
    9 April, Rio Tinto and Turquoise Hill Resources (TRQ) announced they
    had entered into a binding Heads of Agreement for an updated funding
    plan for the completion of the Oyu Tolgoi underground project. The
    funding plan addresses the estimated remaining funding requirement of
    approximately $2.3 billion, building on and replacing the arrangements
    established in the Memorandum of Understanding that Rio Tinto and TRQ
    previously entered into on 9 September 2020.
  • The Mongolian Tax
    Authority required payment from Oyu Tolgoi for the full amount of the
    2018 assessment (2013-2015 years) and 2020 assessment (2016-2018 years) –
    a total of approximately $356m. In line with Mongolian legislation, Oyu
    Tolgoi has paid these amounts in full, however, the amounts are subject
    to an ongoing arbitration process.


[1]
The level of accuracy of the remaining capital and schedule within the
definitive estimate is at a better level than feasibility study. The
2020 estimate assumed COVID-19 restrictions in 2021 that were no more
stringent than those experienced in September 2020 and noted that should
COVID-19 constraints continue beyond 2021 or should the COVID-19
situation escalate further in 2021 leading to tougher restrictions,
additional costs and schedule impacts will arise. Since the definitive
estimate, Mongolia has implemented additional restrictions in response
to community transmission cases, and in March 2021 the first cases of
COVID-19 were identified at Oyu Tolgoi resulting in temporary site
shutdown, quarantine measures and further travel and movement
restrictions. The impact of these additional restrictions, which are
beyond those experienced in September 2020, is ongoing and still to be
determined.


Comments

Leave a Reply

Your email address will not be published. Required fields are marked *